| Course Code | 6032EE |
| Course Title | Power Systems |
| Programme | B.Eng. in Electrical and Electronic Engineering |
| University | Coventry University, delivered at PSB Academy Singapore |
| Assessment | Coursework 2026, individual report (issued September 2026) |
| Questions | Three questions: Q1 33 marks, Q2 33 marks, Q3 34 marks |
| Software | PowerWorld Simulator (Question 3) |
| Format and Referencing | Word report converted to PDF, Times New Roman or Arial 12, table of contents; Coventry University Harvard referencing |
The 6032EE Power Systems coursework combines calculation, research and simulation. Students work through solar sizing and power station load factor problems, write a 3,000-word report on a modern power plant in Europe, the USA or Australia, and model a three-bus network in PowerWorld to run a load flow analysis.
General Instructions
- Answer all three questions in a single report, in the same order, with clear headings; start each full question on a new page.
- The cover page must show the university, the course, your name, student number and submission date, and the report must include a table of contents.
- Cite references for all data, graphs, charts, figures, illustrations and diagrams taken from other sources, following the Coventry University Harvard guide.
- Prepare the report in Microsoft Word using one consistent font (Times New Roman or Arial, size 12) and submit it as a PDF on Blackboard.
Question 1 (33 marks)
- The average solar energy received by a surface over one month is 5 kWh/m² per day. Explain the term solar insolation, then determine the peak sun hours for that month. (3 marks)
- A small electrical installation needs an average of 2,500 Wh (2.5 kWh) per day, and the annual solar insolation at the site is 5 kWh/m² per day. Using 12 V solar panels rated at 180 W, calculate the number of panels required. (12 marks)
- A power station has a maximum demand of 12 MW, an annual load factor of 50% and a utilisation factor of 40%. Determine the energy generated per year, then find the reserve capacity of the plant. (10 marks)
- The maximum demand of a power plant is 60 MW. Calculate the installed capacity needed to give a reserve margin of 20%. (8 marks)
Question 2 (33 marks)
Prepare a report on any recent modern power plant in Europe, the USA or Australia (3,000 words ±10%, references in an appendix not counted). Use information from electricity authorities, IEEE, IET, the International Energy Agency or similar bodies, and cite all data and figures. Suggested sections:
- Introduction (6 marks): background information on the chosen power plant.
- Electricity Generation Operation (10 marks): generation operation, installed capacity, maximum demand and reserve margin from reliable sources, presented as graphs or charts, with analysis of any generation mix.
- Choices of Renewable Energy (12 marks): facts on TWO types of renewable energy and their contribution to generation, shown in a graph or chart, plus the country’s future renewable energy plans (also charted) with your comments.
- Summary and Conclusions (5 marks): observations, conclusions and the major features of the plant.
Question 3 (34 marks)
A three-bus power system (Figure Q3) has the following data.
| Bus | Voltage (kV) | Initial pu | Remarks |
| BUS_1 | 33 | 1 | Slack bus |
| BUS_2 | 33 | 1 | |
| BUS_3 | 11 | 1 |
| Generator | Bus | Reactance | MW (min/max) | MVAR (min/max) | AGC / AVR / Enforce MW limits |
| 1 | 1 | 0.01 | 0 / 2000 | -9900 / 9900 | Yes / Yes / Yes |
| 2 | 2 | 0.01 | 0 / 2000 | -9900 / 9900 | Yes / Yes / Yes |
| Line | Length | Parameters | Type |
| 1-2 | 20 km | R = 0.01 Ω/km, X = 0.015 Ω/km | Overhead line (admittance ignored, short line) |
| 1-3 | 10 km | R = 0.005 Ω/km, X = 0.001 Ω/km, B = 0.001 mho/km | Underground cable |
| 2-3 | 10 km | R = 0.005 Ω/km, X = 0.001 Ω/km, B = 0.001 mho/km | Underground cable |
Load: 100 MW and 50 MVAr at Bus 3.
- From the line data, theoretically find the R(pu) and X(pu) values and comment on the per-unit values obtained. (10 marks)
- Construct the network in PowerWorld using the data in Tables Q3.A to Q3.D and include the network before simulation in your report, showing voltage and phase angle at every bus and real and reactive power at both ends of every line. (12 marks)
- From the Tools menu choose Solve and perform the load flow analysis; include the simulated (or during-simulation) diagram with all field values clearly shown. (12 marks)