| University | Singapore University of Social Science (SUSS) |
| Subject | BUS353: Project management Course Work |
Question 4
After discussion with the CEO, it has been decided that the company do not wish to incur additional cost and is fine to delay the project completion time. Resolve the conflict and schedule issues accordingly to the MS Project File. The baseline is set in MS Project. The project proceeded on.
After discussion with the CEO, it has been decided that the company do not wish to incur additional cost and is fine to delay the project completion time. Resolve the conflict and schedule issues accordingly to the MS Project File. The baseline is set in MS Project. The project proceeded on.
Two incidents occurred during the project implementation period:
1. During the “setup of cabling work” (Table 1 – Activity 8), contractor from Lenovo Services informed Raman that there is a shortage of a key hardware component from Germany, an alternative brand has been procured from Taiwan. While cost remains the same, it will only arrive later and resulting in “Install system hardware” (Table 1 – Activity 9) to start 2 days later from its original start date.
2. Due to this change in hardware component, contractor from NTT Data advised that an extra set of programming code has to be implemented due to the proprietary interface of this new hardware and an extra charge of $4,000 will be billed to Kopi Shop for “Install POS system software” (Table 1 – Activity 10). The CEO agrees to all the changes in the two incidences. You shall implement all the necessary changes and modify the deadline accordingly.
Stuck with a lot of homework assignments and feeling stressed ? Take professional academic assistance & Get 100% Plagiarism free papers
The project progressed on till completion. The system was handed over to Kopi Shop.
Set the Status Date to 3 working days after the project completion. Update the project (Project –> Update Project –> Entire Project).
Question 4a
Prepare in a single diagram the Tracking Gantt Chart view of MS Project with Information (I), Task Mode, Task Name, Duration, Start Date, Finish Date and Resource columns shown. State and comment on the project completion date. Question 4b
Show a MS Project Cost Report or Table with Cost Performance Index (CPI). State the cost values for Budgeted at Completion (BAC), and Estimated at Completion (EAC). Verify the final CPI manually using these values. Question 4c
Appraise whether the project is a success. Recommend two (2) ways to prevent some of the problems from happening in similar projects in future.
Prepare in a single diagram the Tracking Gantt Chart view of MS Project with Information (I), Task Mode, Task Name, Duration, Start Date, Finish Date and Resource columns shown. State and comment on the project completion date. Question 4b
Show a MS Project Cost Report or Table with Cost Performance Index (CPI). State the cost values for Budgeted at Completion (BAC), and Estimated at Completion (EAC). Verify the final CPI manually using these values. Question 4c
Appraise whether the project is a success. Recommend two (2) ways to prevent some of the problems from happening in similar projects in future.
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Native Singapore Writers Team
- 100% Plagiarism-Free Essay
- Highest Satisfaction Rate
- Free Revision
- On-Time Delivery
Get Help By Expert
Empower your journey through BUS353 Project Management Coursework with our specialized aid. Offering assignment help online and Homework Help Singapore, we provide tailored support to Singaporean students. Let our expertise propel you towards academic excellence, ensuring your projects shine with precision and proficiency.
Answer
Looking for Plagiarism free Answers for your college/ university Assignments.
Recent Solved Questions
- GSS503 Navigating Risk in an Interconnected World Course Tutor-Marked Assignment 01, 2026
- GSS501 Global Crime Prevention and Security Management Tutor-Marked Assignment 01, 2026
- PSB6012CL Business Research Methods Assignment Brief 2026 | Coventry University
- MTH109 Calculus Tutor-Marked Assignment 1, 2026 | SUSS
- BUS286 Corporate Finance Assignment 2026 | Murdoch University
- HFSY359 Fatigue Management Tutor Mark Assignment Question 2026 | SUSS
- BSE313 Sport Coaching Tutor-Marked Assignment 2 Question 2026 | SUSS
- 6079MP Final Coursework Assignment 2026 | Coventry University
- IBUS2004 Managing International Business Assessment 1 Brief 2026 | UON
- BSL305 Company Law Assignment 2026 | Murdoch University
