QUESTIONS
Question 1
Identify and briefly describe any THREE (3) responsibilities of the Consultant Quantity Surveyor during each of the following stages of a construction project.
(a) Feasibility and design
(b) Tender documentation and tender award
(c) Post contract work
Question 2
(a) Identify and explain with the help of diagrams the CEMS rules required to be applied to the measurement of oversite excavation and the subsequent disposal of the excavated materials off site.
(b) Interpret Figures Q2.1 and Q2.2 and take-off quantities for the oversite excavation and disposal of excavated materials off site.
Specifications:
1. The existing ground level is at 20.100.
2. All excavated materials shall be disposed off site to an approved tip
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Native Singapore Writers Team
- 100% Plagiarism-Free Essay
- Highest Satisfaction Rate
- Free Revision
- On-Time Delivery
Question 3
Apply measurement techniques and interpret the scope of C & S work with reference to Figures Q3.1 to Q3.3 to prepare a take-off list with associated CEMS clauses and the units of measurement for the following works:
(a) Excavation, concrete and formwork for the pile caps and column stumps including the adjustment of quantities for excavation work.
(b) Reinforcement for pile caps & column stump
(c) Precast reinforced concrete piles.
Question 4
Apply measurement techniques and interpret the scope of C & S work with reference to Figures Q3.1 to Q3.3 to take-off quantities for the following works:
(a) Excavation, concrete and formwork for the pile caps and column stumps including the adjustment of quantities for excavation work.
(b) Reinforcement for pile caps and column stump.
(c) Precast reinforced concrete
working piles

Figure Q2.1 – Foundation Plan (NTS)

Figure Q2.2 – Section Through Slab (NTS)

Figure Q3.1 – Foundation & Piling Plan (NTS)

Figure Q3.2 – Pilecap Details (NTS)

Figure Q3.3 – Pilecap Reinforcement Details (NTS)
Stuck with a lot of homework assignments and feeling stressed ? Take professional academic assistance & Get 100% Plagiarism free papers
Do you need assistance with your BPM209 Cost Management for C&S Works Tutor-Marked Assignment One? Our Singapore assignment help service is here for you! We offer expert guidance and tailored solutions, including Tutor-Marked Assignment Answers to help you understand the material better. Plus, we provide Management Assignment Samples for SG scholars to give you a clear idea of what is expected. Don’t hesitate to reach out—let our professionals support you in achieving your academic goals!
Looking for Plagiarism free Answers for your college/ university Assignments.
- ICT340 Application Analysis and Design End-of-Course Assessment 2026
- MGT304 Business Consultancy Project Assessment Brief 2026 | MDIS
- FMT306 Strategic Asset, Property and Facilities Management End-of-Course Assessment January Semester 2026
- PSY373 Psychology of Nonverbal Behaviours End-of-Course Assessment January Semester 2026 | SUSS
- MGE302 Applied Economics Individual Assignment 2026 | SIM
- POL351 Comparative Politics in Southeast Asia End-of-Course Assessment 2026 | SUSS
- SOC313 Sociology of Education End-of-Course Assessment 2026 | SUSS
- BPM213 Procurement Management Tutor-Marked Assignment 2, 2026 | SUSS
- MNGT3013 Innovation Management Assessment 1, 2026 | University of Newcastle
- BPM203 Construction Project Management Group-based Assignment 01, 2026 | SUSS