Question 1
Identify and briefly describe any THREE (3) responsibilities of the Consultant Quantity Surveyor during each of the following stages of a construction project.
(a) Feasibility and design
(b) Tender documentation and tender award
(c) Post contract work
Question 2
(a) Identify and explain with the help of diagrams the CEMS rules required to be applied to the measurement of oversite excavation and the subsequent disposal of the excavated materials off site.
(b) Interpret Figures Q2.1 and Q2.2 and take-off quantities for the oversite excavation and disposal of excavated materials off site.
Specifications:
1. The existing ground level is at 20.100.
2. All excavated materials shall be disposed off site to an approved tip
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Native Singapore Writers Team
- 100% Plagiarism-Free Essay
- Highest Satisfaction Rate
- Free Revision
- On-Time Delivery
Question 3
Apply measurement techniques and interpret the scope of C & S work with reference to Figures Q3.1 to Q3.3 to prepare a take-off list with associated CEMS clauses and the units of measurement for the following works:
(a) Excavation, concrete and formwork for the pile caps and column stumps including the adjustment of quantities for excavation work.
(b) Reinforcement for pile caps & column stump
(c) Precast reinforced concrete piles.
Question 4
Apply measurement techniques and interpret the scope of C & S work with reference to Figures Q3.1 to Q3.3 to take-off quantities for the following works:
(a) Excavation, concrete and formwork for the pile caps and column stumps including the adjustment of quantities for excavation work.
(b) Reinforcement for pile caps and column stump.
(c) Precast reinforced concrete
working piles

Figure Q2.1 – Foundation Plan (NTS)

Figure Q2.2 – Section Through Slab (NTS)

Figure Q3.1 – Foundation & Piling Plan (NTS)

Figure Q3.2 – Pilecap Details (NTS)

Figure Q3.3 – Pilecap Reinforcement Details (NTS)
Stuck with a lot of homework assignments and feeling stressed ? Take professional academic assistance & Get 100% Plagiarism free papers
Do you need assistance with your BPM209 Cost Management for C&S Works Tutor-Marked Assignment One? Our Singapore assignment help service is here for you! We offer expert guidance and tailored solutions, including Tutor-Marked Assignment Answers to help you understand the material better. Plus, we provide Management Assignment Samples for SG scholars to give you a clear idea of what is expected. Don’t hesitate to reach out—let our professionals support you in achieving your academic goals!
Looking for Plagiarism free Answers for your college/ university Assignments.
- A2859C Pharmacotherapeutics I Graded Assignment Brief 2026
- A3750C Dietary Supplements Graded Assignment Individual Report 2026
- Introduction to Accounting Assessment Questions | SMU
- B2079C Job and Labour Market Analysis Coursework Assessment AY2025 Term 4
- B2089C Career Development and Counselling Coursework Assessment AY2025
- PSB501EN Mechanical Engineering Systems Assessment Brief | CU
- 303SD Structural Steel Design Project Brief Report SEM 2 | Ngee Ann Polytechnic
- Security Risk Management Individual Project Assignment | SIT
- 63MBID Information Management and Digital Intelligence Coursework | UNAM
- BA8081 Innovation Management Individual CA 2 AY2024/25 SEM 2 | Singapore Polytechnic