    This sustainable energy systems sample extract shows how a strong answer to the Singapore Institute of Technology project on Modules 2 and 3 can be organised: a BESS sized from the load profile, five HOMER cases, demand response and a recommendation. It follows the Modules 2 and 3 BESS sizing and HOMER smart grid brief. The question page does not print the campus data, so every figure below is illustrative, invented for teaching, and must be replaced by your own dataset and HOMER outputs. For the method behind each step, read our guide on how to size a BESS and build HOMER smart grid cases. The answer is abridged.

    Planning table

    Brief part Deliverable What markers look for
    Load analysis Statistics, peak events, four profiles Datasets reconciled; load factor and peak-to-average ratio calculated
    Storage technologies Comparison of at least two Cost, efficiency, depth of discharge, life and safety judged against daily cycling
    BESS sizing Power, usable and nominal energy, candidate range A chain from the load curve to the size, not an arbitrary entry in HOMER
    Five HOMER cases Technical, economic and carbon table All cases compared, not only HOMER’s top-ranked result
    Demand response and architecture Three participation levels, constraints, layered design Quantified response with rebound and comfort limits

    Check your own brief for the exact mark split before copying any of these proportions.

    Hire a Professional Essay & Assignment Writer for completing your Academic Assessments

    Native Singapore Writers Team

    • 100% Plagiarism-Free Essay
    • Highest Satisfaction Rate
    • Free Revision
    • On-Time Delivery

    Module 2: load analysis and storage design

    Load statistics (illustrative)

    The half-hourly kWh readings are converted to kW by multiplying by two, then checked against the 5-minute data so that both datasets give the same annual total. The 5-minute series is used for peak duration, because half-hourly averaging hides short spikes.

    Metric Value Working
    Maximum demand 6.0 MW Highest half-hourly kW
    Average demand 3.2 MW 28,032 MWh / 8,760 h
    Load factor 53.3% 3.2 / 6.0
    Peak-to-average ratio 1.88 6.0 / 3.2
    Time above 5.2 MW about 110 h a year Counted from the demand-duration curve

    A load factor near 53% and a short tail of high demand are the conditions in which peak shaving is worth testing, because a small battery can remove a high-cost slice of the peak (Hesse et al., 2017).

    Storage technology comparison

    Criterion Lithium iron phosphate (LFP) Vanadium redox flow
    Round-trip efficiency (typical) About 90% About 65 to 75%
    Usable depth of discharge About 90% Close to 100%
    Cycle and calendar life Several thousand cycles; calendar ageing and degradation must be modelled Very long cycle life; electrolyte lasts, pumps and stacks need maintenance
    Footprint and energy density Compact, important on a campus Large tanks and a bigger footprint
    Safety and environment Thermal-runaway risk managed by BMS, fire design and recycling plans Non-flammable electrolyte; vanadium handling and end-of-life recovery
    Fit for daily cycling of 2 to 3 hours Strong Technically suitable, weaker on cost and space

    The ranges are typical published values and should be replaced by supplier data in your own work. LFP is carried forward because of its efficiency, footprint and suitability for daily cycling.

    Preliminary sizing

    Power rating: the design peak is 6.0 MW and the target peak is set at 5.2 MW from the demand-duration curve, so the shaving requirement is 0.8 MW. A 10% margin gives 0.88 MW, rounded to a 0.9 MW rating with a 1.0 MW converter. The load peak of 6.0 MW is used rather than the lower post-PV peak of 5.9 MW because solar output cannot be relied on at the evening peak; the 0.1 MW difference is part of the margin.

    Usable energy: on the design peak day the area above the 5.2 MW target is summed from the half-hourly profile.

    Half-hour block 1 2 3 4 5 6 7 8 9 10
    Excess above 5.2 MW (kW) 150 300 450 600 800 700 550 400 250 100

    The excess totals 4,300 kW, so the usable energy is 4,300 x 0.5 h = 2,150 kWh, or 2.15 MWh.

    Nominal energy: usable energy is divided by depth of discharge (0.90), one-way discharge efficiency (the square root of 0.90 round-trip, about 0.949) and availability (0.98). Nominal energy = 2.15 / (0.90 x 0.949 x 0.98) = 2.57 MWh, rounded to 2.6 MWh. The result is a C-rate of about 0.38C on the 1.0 MW converter.

    Candidate range for HOMER: power 0.5, 0.75, 1.0 and 1.25 MW; energy 1.5, 2.0, 2.6, 3.0 and 3.5 MWh. HOMER then tests this window instead of an arbitrary single battery (HOMER Energy, n.d.).

    Module 3: HOMER cases and demand response

    Assumptions (illustrative)

    Project life 25 years, real discount rate 6%, grid energy charge S$0.20/kWh, demand charge S$20/kW-month, PV 3 MWp at S$1,200/kWp yielding 1,400 kWh/kWp (4,200 MWh a year), BESS S$650/kWh installed with a 12-year life and a replacement at 60% of the original cost, DR control and metering S$150,000. Grid emission factor 0.40 kg CO2/kWh, an assumption to be replaced by the current factor published by the Energy Market Authority. Operating costs are 1.5% (PV), 2% (BESS) and 5% (DR) of capital cost a year.

    The battery is assumed to cycle about 250 times a year, so about 60 MWh of annual import is added by round-trip losses (the flat energy price makes the shifting itself cost-neutral).

    Demand response design

    Flexible load is taken as 3.0 MW at the peak (chillers, air-conditioning set-points, EV charging). Three participation levels are tested: DR-Low 5% (0.15 MW), DR-Medium 10% (0.30 MW) and DR-High 15% (0.45 MW). Constraints: events of up to 2 hours, no more than 20 events a year, eligible hours 14:00 to 18:00 on weekdays, laboratories and critical loads excluded, comfort limits on indoor temperature, and 90% of shifted energy returning within two hours as rebound. DR-Medium is used in Cases 3 and 4. Singapore’s Energy Market Authority has reported that demand response has already saved electricity buyers more than S$700 million between 2023 and mid-2024, which supports treating DR as a real resource (Energy Market Authority, 2024).

    Comparison of the five cases (illustrative)

    Case Capital (S$m) Annual grid bill (S$m) NPC (S$m) LCOE (S$/kWh) Peak (MW) Import (GWh) Renewable fraction CO2 (kt/yr)
    0 Grid only 0.00 7.05 90.08 0.2514 6.0 28.03 0% 11.21
    1 Grid + PV 3.60 6.18 83.32 0.2325 5.9 23.83 15.0% 9.53
    2 Grid + PV + BESS 5.29 6.03 83.95 0.2343 5.2 23.89 15.0% 9.56
    3 Grid + PV + DR 3.75 6.11 82.65 0.2306 5.6 23.83 15.0% 9.53
    4 Grid + PV + BESS + DR 5.44 5.95 83.28 0.2324 4.9 23.89 15.0% 9.56

    Worked check for Case 2: energy charge 23,892 MWh x S$0.20/kWh = S$4.78 million, demand charge 5,200 kW x S$20 x 12 = S$1.25 million, giving S$6.03 million a year. NPC includes capital, the discounted BESS replacement, and 25 years of operating and grid costs, discounted with an annuity factor of 12.78. LCOE is the annualised NPC (capital recovery factor 0.0782) divided by the 28,032 MWh served; the NPC concept follows HOMER’s life-cycle definition (HOMER Energy, n.d.).

    Economic and technical reading

    PV delivers the largest gain: NPC falls by S$6.76 million against Case 0 and the renewable fraction is 15.0% (4,200 / 28,032). PV barely changes the peak, from 6.0 to 5.9 MW, because the peak occurs when solar output is low.

    Storage value, Case 2 against Case 1: peak falls by 0.7 MW and the annual bill by S$156,000, but the extra capital is S$1.69 million. Net of S$33,800 of extra operating cost, simple payback is 1.69 / 0.1222 = 13.8 years, longer than the assumed 12-year battery life, and NPC rises by S$0.63 million. On these inputs the BESS breaks even only at about S$490/kWh installed.

    DR value, Case 3 against Case 1: S$72,000 a year saved for S$150,000 of capital and S$7,500 of operating cost, a simple payback of 2.3 years, and the lowest NPC of the five cases.

    Case 4 gives the deepest peak cut (4.9 MW, 18% below baseline) and the lowest annual bill, but its NPC is S$0.63 million above Case 3. Emissions fall 15% from 11.21 to 9.53 kt a year with PV; the BESS slightly raises them through losses.

    Smart-grid architecture and AMI

    Field layer: revenue-grade smart meters at the campus incomer, PV inverters, BESS and each major chiller plant, recording bidirectional kWh and kW at 5-minute intervals, time-synchronised by NTP. Building layer: gateways and the building management system, using BACnet/IP for building plant and Modbus TCP for inverters and the BMS of the battery. Supervisory layer: SCADA, an energy management system that dispatches the BESS and DR events, and a historian. Enterprise layer: a dashboard, tariff data and reporting. Wired Ethernet or fibre is used for control signals and cellular or wireless links only for remote monitoring, with network segmentation for cybersecurity.

    Recommendation

    Case 3 (PV plus DR) is preferred on cost: lowest NPC (S$82.65 million), lowest LCOE and a payback of 2.3 years on the DR element, with the same emissions as Case 1. The battery should be treated as a staged option: Case 4 gives the lowest peak and most flexibility, so it becomes attractive if installed cost falls towards S$490/kWh or the demand charge or DR incentives rise. The trade-off is therefore cost against peak reduction and resilience, not simply HOMER’s cheapest result.

    Need help with a project like this? Our electrical power engineering assignment help and report writing help pages explain what support is available, you can browse the wider engineering assignment help service, or submit your assignment details for a tailored quote. Other SIT briefs are listed in our Singapore Institute of Technology question library.

    References

    Energy Market Authority (2024) New initiatives to harness demand flexibility potential in Singapore. Media release, 21 October. Available at: https://www.ema.gov.sg/news-events/news/media-releases/2024/new-initiatives-to-harness-demand-flexibility-potential-in-sg

    Hesse, H.C., Schimpe, M., Kucevic, D. and Jossen, A. (2017) ‘Lithium-ion battery storage for the grid: a review of stationary battery storage system design tailored for applications in modern power grids’, Energies, 10(12), article 2107. Available at: https://www.mdpi.com/1996-1073/10/12/2107

    HOMER Energy (n.d.) Total net present cost in HOMER. HOMER Knowledge Base. Available at: https://homerenergy.com/docs/knowledgebase/article/total-net-present-cost-in-homer/

    Prepared by

    Singapore Assignment Help Editorial Team
    Singapore Assignment Help Editorial Team

    This model answer was prepared by our subject desk in response to a real assignment brief we received. It shows one way to approach the task and is meant as a study guide, not for submission.