Question 1
You are one of three carpenters assigned to complete a small construction project. Right before the start of the project, one of your fellow carpenters was hospitalized and will not be available to work on the project.
Apply resource scheduling technique to a resource-constrained schedule in the loading chart that follows, to see how long the project will take with only 2 carpenters. Be sure to record the order in which you schedule the activities using scheduling heuristics.
Activities A, B, C, D, E, G, and H require 2 carpenters to complete. Activity F requires only 1 carpenter. No. splitting of activities is possible.
Compute the following:
(a) Resource distribution
(b) Minimum time in which the project can be finished
(c) Conditions under which the project can be finished in 15 days or the last days

Stuck with a lot of homework assignments and feeling stressed ? Take professional academic assistance & Get 100% Plagiarism free papers
Question 2
You are to demonstrate the understanding of Project Schedule and Control:
Based on the tabulation of the project program for a Project in Table Q2, compute the following:

(a) Weightage by Activity Name
(b) Provide justification on the basis used to compute the weightage
(c) Value of work done based on the progress information
(d) Compute in percentage the Overall Progress (to 2 decimal places)
(e) Weightage by Activity name after considering the variation
(f) Explain the rationale behind your response in 2(e)
(g) Value of work done after the variation, considering there is no change in the Progress
(h) Compute in percentage the Overall Progress after Variation (to 2 decimal places)
SUSS University students can easily find BPM305: Project Scheduling and Control assignment help in Singapore only at Singapore Assignment Help. We have a team of best assignment writers who are available for round the clock assistance to project management students.
Looking for Plagiarism free Answers for your college/ university Assignments.
- 7WBS2009 Financial Management and Analysis Assignment Brief 2026 | SUSS
- 5010MKT Marketing Management Assignment Brief 2026 | Coventry University
- FILM1000 Introduction to Film Studies Assignment Brief 2026 | NTU
- CET206 Full Stack Web Application Development Tutar Marked Assignment Questions 2026 | SUSS
- 7WBS2011 Strategic Management Research Assignment Brief 2026 | PSB Academy
- HBC101 Understanding Contemporary Society: The Social and Behavioural Sciences TMA 01 2026 | SUSS
- SOC365 Popular Culture End-of-Course Assessment Question 2026 | SUSS
- BME317 Biomedical Devices Innovation Tutor-Marked Assignment 2026 | SUSS
- CU6027 Digital Marketing Report Assessment Brief 2026 | SUSS
- RBP020L062V Financial Performance Management Summative Assessment 2026