Question 1
Apply scheduling and control techniques to improve project processes.
The activities involved in the construction of a small project with resource usage for each activity are given in Table 1. Reflect your understanding of resource leveling by computing the following:
(a) Resource distribution
(b) Resource distribution using heuristics
(c) Resource distribution to flatten the peaks but with no change in project time
(d) Minimum time in which the project can be finished by restricting labor to 22 per week
Stuck with a lot of homework assignments and feeling stressed ? Take professional academic assistance & Get 100% Plagiarism free papers
Question 2
Demonstrate an understanding of project schedule and control.
The tabulation below (Table 2) shows a bill of quantity for the construction of an Earth Retaining Structure with the following information:
i. Quantity estimated at the start of the work & Rate quoted by the contractor
ii. Progress updated after 4 months
iii. Quantity of each item of work assessed after 5 months
Compute the following:
(a) Total contract value
(b) Weightage by Diaphragm Walls – by structure and overall
(c) Weightage by Barrette Piles
(d) Provide justification on the basis used to compute the weightage
(e) Value of work done based on the progress information
(f) Compute in percentage the Overall Progress (to 2 decimal places)
(g) Weightage by Activity name after considering the variation
(h) Explain the rationale behind your response in (e)
(i) Compute in percentage the Overall Progress after Variation (to 2 decimal places)
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Native Singapore Writers Team
- 100% Plagiarism-Free Essay
- Highest Satisfaction Rate
- Free Revision
- On-Time Delivery
Maximum SUSS university students unable to complete their BPM305: Project Scheduling and Control Assignment accurately on time. They look for help. We, at Singapore Assignment Help, serve the efficient Project Management Assignment Help and make sure that you are saved from your assignment difficulty. Our Assignment help expert work round the clock to provide you better answers related to project management.
Maximum SUSS university students unable to complete their BPM305: Project Scheduling and Control Assignment accurately on time. They look for help. We, at Singapore Assignment Help, serve the efficient Project Management Assignment Help and make sure that you are saved from your assignment difficulty. Our Assignment help expert work round the clock to provide you better answers related to project management.
Looking for Plagiarism free Answers for your college/ university Assignments.
- BUS 304 Assignment: Strategic Analysis of Accounting Standards & Corporate Ethics
- RBP020L056 A Strategic Management Assignment Report: External & Internal Analysis with Strategic Options for Business Growth
- Capital Budgeting Assignment Report: PIONG Corporation Case Study on Risk & Investment Analysis
- BCAF003 Business Accounting Assignment : Temasek Polytechnic Case Study on Transactions, Equity & Trial Balance
- 304SE Energy Systems Assignment: Boiler Efficiency & 3-Bus Power Flow Case Study with Carbon Emission Analysis
- SM9532 International Expansion Strategy Assignment Report: CAGE, PND & AAA Analysis for Global Market Entry
- PSB6023CL Strategy and International Business Simulation Assignment Report: Automotive Case Study on Strategic Decision-Making and Performance Review
- ESG in Maritime Industry Assignment : Literature Review on Environmental, Social and Governance Practices
- CVE2332 Seepage and Flownet Analysis Assignment : Singapore River Cofferdam Case Study for Cost-Effective Sheet Pile Design
- DSWSH MC2 Electronic Security Assignment: Protection in Depth Plan for American International School (AIS) Singapore