BPM305 TUTOR-MARKED ASSIGNMENT TWO (TMA02)
This assignment is worth 14% of the final mark for BPM305 Project Scheduling and Control.
The cut-off date for this assignment is 25 March 2026, 2355 hrs.
Note to Students:
You are to include the following particulars in your submission: Course Code, Title of the TMA, SUSS PI No., Your Name, and Submission Date.
Question 1
Demonstrate understanding of Project Control.
Peach manufactures high tech devices for public. Currently, the executive team is developing a new version of their smartphone. As with all their products, they intend to design the smartphone to meet current trends and manufacture the device in-house to maintain quality standards. Estimates have been made for the development process to bring the project to the manufacturing stage. The company aims to meet the product specifications, prioritize adherence to the project timeline, and is prepared to incur additional costs to achieve a tighter schedule.
Use the information provided in Table Q1 and demonstrate your competency in using Microsoft project Software by:
| Activity | Duration | Predecessor | Cost |
| Initialisation Phase | |||
| Sprint – Team Formation | |||
| Selection Process | 8 days | $2,500.00 | |
| Contract Finalisation | 10 days | 4 | $3,000.00 |
| Legal Processing | 9 days | 5 | $5,000.00 |
| Sprint – Project Proposal | |||
| Requirement Analysis | 8 days | 6 | $2,000.00 |
| Develop Objectives | 8 days | 8 | $1,000.00 |
| Risk Assessment | 7 days | 9 | $1,500.00 |
| Budgeting | 10 days | 9 | $2,000.00 |
| Client Review and Sign-off | 1 day | 11,10 | $5,000.00 |
| Design Phase | |||
| Sprint – Logo Design | |||
| Research | 9 days | 12 | $8,000.00 |
| Colour Scheming | 7 days | 15 | $5,000.00 |
| Sprint – Interface Design | |||
| Colour Scheming | 7 days | 16 | $5,000.00 |
| Page Icons | 9 days | 16 | $4,000.00 |
| Layout Design | 12 days | 19,18 | $6,000.00 |
| Sprint – Prototyping | |||
| Evaluation | 7 days | 20 | $2,000.00 |
| Finalisation | 3 days | 22 | $2,000.00 |
| Client Review and Approval | 9 days | 23 | $2,000.00 |
| Execution Phase | |||
| Sprint – Theoretical Background | |||
| Social Incentives | 15 days | 12 | $4,000.00 |
| Item Detection | 17 days | 12 | $4,000.00 |
| Image Analysis | 17 days | 12 | $2,000.00 |
| Sprint – Software Development | |||
| Social Incentives Algorithm | 21 days | 27 | $6,000.00 |
| Item Detection Algorithm | 23 days | 31SS,28 | $2,000.00 |
| Image Analysis Algorithm | 25 days | 29 | $2,000.00 |
| Sprint – Component Integration | |||
| Lining Modules | 9 days | 32 | $4,000.00 |
| Evaluation | 7 days | 35 | $2,000.00 |
| Finalisation | 3 days | 36 | $2,000.00 |
| Sprint – Product Testing | |||
| Acquire Testing Hardware | 5 days | 37 | $20,000.00 |
| Image Analysis Testing | 10 days | 39 | $10,000.00 |
| Item Detection Testing | 12 days | 39 | $10,000.00 |
| Beta Testing | 10 days | 41,40 | $6,000.00 |
| Finalisation / Maintenance Phase | |||
| Sprint – Client Final Review | |||
| Client Approval and Sign-off | 8 days | 24,42 | $2,000.00 |
| Handover | 6 days | 45 | $2,000.00 |
| Sprint – Commercial App | |||
| Develop Product Manual | 14 days | 46 | $10,000.00 |
| Commercialise App | 23 days | 46 | $20,000.00 |
| Sprint – Initial Maintenance | |||
| Analyse Feedback | 12 days | 49 | $6,000.00 |
| Performance testing | 16 days | 49 | $20,000.00 |
| Developing New Update | 10 days | 51,52 | $10,000.00 |
Table Q1
(a) Organise the tasks in Table Q1 and create a project schedule. Assume the project will begin on 1st October 2025. Use a standard workweek for the schedule and determine the project’s completion date.
(15 marks)
(b) Attach a MS project file of the above, showing the critical path.
(10 marks)
(c) Generate the project cash flow and represent it as a monthly bar chart and S-Curve.
(15 marks)
(d) Suggest any improvements to the program.
(10 marks)
Question 2
The duration and direct cost for each activity in the network of a small construction contract under both normal and crash conditions are given in Table Q2.
Determine the following:
(a) Cost slope for each activity.
(5 marks)
(b) Normal cost of the project.
(5 marks)
(c) Cost associated with each duration till a stable critical path.
(21 marks)
(d) Provide reasoning for choosing the activity at each stage of Q2(c) above.
(7 marks)
(e) Least-cost (direct and total) and crash duration.
(6 marks)
(f) What conclusion can you draw from the results?
(6 marks)
For your computation, use an Indirect (overhead) cost of $125 per day.
| Normal | Crash | ||||
| Activity | Preceded by | Duration (day) | Cost ($) | Duration (day) | Cost ($) |
| A | 12 | 7,000 | 10 | 7,200 | |
| B | A | 8 | 5,000 | 6 | 5,300 |
| C | A | 15 | 4,000 | 12 | 4,600 |
| D | B | 23 | 5,000 | 23 | 5,000 |
| E | B | 5 | 1,000 | 4 | 1,050 |
| F | C | 5 | 3,000 | 4 | 3,300 |
| G | C, E | 20 | 6,000 | 15 | 6,300 |
| H | F | 13 | 2,500 | 11 | 2,580 |
| I | D,G,H | 12 | 3,000 | 10 | 3,150 |
Table Q2: Duration and Direct Cost of Each Activity
—- END OF ASSIGNMENT —-
Hire Professional Project Management Assignment Helper For Your BPM305 TMA 02
Native Singapore Writers Team
- 100% Plagiarism-Free Essay
- Highest Satisfaction Rate
- Free Revision
- On-Time Delivery
Many SUSS students struggle to complete the BPM305 Project Scheduling and Control TMA02 because tasks like creating a project schedule in Microsoft Project, identifying the critical path, preparing project cash flow charts, and analysing crash cost calculations can be difficult to understand. Some students also run short of time while managing multiple deadlines. If you are facing the same issue, there is no need to worry. Singapore Assignment Help provides reliable Project Scheduling and Control Assignment Help aligned with SUSS requirements. You can also explore our SUSS assignment samples to see the type of project management assignments we have delivered before. Hire our professional TMA assignment helper today and get a custom BPM305 assignment answer written only for you.
Looking for Plagiarism free Answers for your college/ university Assignments.
- HRM263 Team Dynamics End-of-Course Assessment January 2026 | SUSS
- BPM207 Cost Management for Architectural Works Tutor-Marked Assignment Two 2026 | SUSS
- BPM309 Cost Management for M&E Works Tutor-Marked Assignment Two 2026 | SUSS
- AVM345 Airline Operations and Planning End-of-Course Assessment 2026 | SUSS
- ICT302 Generative AI: Theory and Practice End-of-Course Assessment 2026 | SUSS
- Thermodynamics Project Questions 2026 | Nanyang Technological University
- GSS503 Navigating Risk in an Interconnected World Course Tutor-Marked Assignment 01, 2026
- GSS501 Global Crime Prevention and Security Management Tutor-Marked Assignment 01, 2026
- PSB6012CL Business Research Methods Assignment Brief 2026 | Coventry University
- MTH109 Calculus Tutor-Marked Assignment 1, 2026 | SUSS