University | Singapore University of Social Science (SUSS) |
Subject | BPM305: Project Scheduling and Control |
Question 1
Apply scheduling and control techniques to improve project processes.
For a project with the information as in Table 1, it is required to reduce the project duration.
Determine the following:
- Cost slope for each activity
- The normal cost of the project
- The cost associated with each duration till a stable critical path.
- Least-cost (direct and total) and crash duration
- Provide reasoning for choosing the activity at each stage of (c) above
- What conclusion can you draw from the results?
For your computation use Indirect (overhead) costs of $100 per day.
Hire a Professional Essay & Assignment Writer for completing your Academic Assessments
Native Singapore Writers Team
- 100% Plagiarism-Free Essay
- Highest Satisfaction Rate
- Free Revision
- On-Time Delivery
Question 2
Appraise earned value for a project.
Your Company has a contract to excavate 1 km of pipeline. The trench is 1.5 m wide and 2 m deep. They use an excavator to excavate. The excavator has a 1.5 m3 bucket. The soil has a swell factor of 25%. The trucks available to carry the excavated soil are of 12 m3 capacity.
The estimated excavator cycle (excavate, swing, load, swing) is 1.5 minutes. The dumping area for the excavated soil is about 12 km away. An empty truck can travel at a speed of 50 km/h. When fully loaded, its speed is reduced to 35 km/h. Allow 3 minutes for waiting at traffic lights and 1.5 minutes for dumping the soil.
Due to extremely hot weather, 50 minutes of work would require 1 hour to complete for the trucks. The daily cost of operating the excavator and truck are $700 and $400, respectively. The daily overhead charges for excavation manpower comprising, supervisor, banksman, and others are $300.
(a) Determine the optimal number of trucks (for minimum costs), the total costs, and the duration of the excavation operation. Assume 8 hours working time per day.
(b) If the trench must be supported, and each crew can strut 5 m of trench per hour, how many trenching crews will you require to maintain the production rate of your earlier decision?
Buy Custom Answer of This Assessment & Raise Your Grades
Writing BPM305: Project Scheduling and Control Assignment is not an easy job for SUSS university students. Most of the time they stuck to finish their assignments. Don’t worry! Singapore Assignment Help will help you to complete your homework. We have a panel of experienced and qualified SUSS University Experts, who provide quality solutions on project management assignments so that you could achieve a higher rank in your academics area.
Looking for Plagiarism free Answers for your college/ university Assignments.
- BUS 304 Assignment: Strategic Analysis of Accounting Standards & Corporate Ethics
- RBP020L056 A Strategic Management Assignment Report: External & Internal Analysis with Strategic Options for Business Growth
- Capital Budgeting Assignment Report: PIONG Corporation Case Study on Risk & Investment Analysis
- BCAF003 Business Accounting Assignment : Temasek Polytechnic Case Study on Transactions, Equity & Trial Balance
- 304SE Energy Systems Assignment: Boiler Efficiency & 3-Bus Power Flow Case Study with Carbon Emission Analysis
- SM9532 International Expansion Strategy Assignment Report: CAGE, PND & AAA Analysis for Global Market Entry
- PSB6023CL Strategy and International Business Simulation Assignment Report: Automotive Case Study on Strategic Decision-Making and Performance Review
- ESG in Maritime Industry Assignment : Literature Review on Environmental, Social and Governance Practices
- CVE2332 Seepage and Flownet Analysis Assignment : Singapore River Cofferdam Case Study for Cost-Effective Sheet Pile Design
- DSWSH MC2 Electronic Security Assignment: Protection in Depth Plan for American International School (AIS) Singapore