DEEP FOUNDATION
1. SCENARIO
An apartment building is to be constructed with a rectangular footprint of 80m by 10m. Below shows the location of the boreholes within the site (bore logs enclosed in the annex). The building may be placed anywhere within the 200m by 150m shaded area.

Design for the most economical foundation configuration for the apartment building and tender this deep foundation project at your most competitive price.
2. SCOPE OF WORKS
The loadings from the apartment building is as follow:
Vertical Permanent Action: 5 kN/m2
Vertical Variable Action: 3 kN/m2
The structure should consist of a maximum of 10 columns with loading on the columns following a tributary distribution (see below figure). The minimum column spacing is 5m.

The choice of deep foundation:
Type of Deep Foundation: Driven or Bored or Combination of Both
Maximum Pile Size: 0.9 m diameter or width
The density of Pile: 2400 kg/m3
Cost of Driven Pile: $ 200,000 per m3 of concrete
Rate of Installation: 0.6 m depth per hour
Cost of Bored Pile: $ 300,000 per m3 of concrete
Rate of Installation: 1.2 m depth per hour
Project Duration: 30 working days (1 month).
Working Days and Hours: 5 working hours per day.
Buy Custom Answer of This Assessment & Raise Your Grades
3. TASK
(a) Interpolate the borehole logs and produce appropriate cross-sections of the soil profile across the site.
(b) Determine the most suitable location to position the footprint of the apartment within the site.
(c) Determine the most suitable location to position the columns of the apartment building.
(d) Design the deep foundations based on the loadings on your columns.
(e) Provide detailed workings deriving the cost of the construction of the deep foundations of the apartment building (i.e. the tender price) that meets the project duration.
(f) Give comments and reflection on the findings of the above tasks

Stuck with a lot of homework assignments and feeling stressed ? Take professional academic assistance & Get 100% Plagiarism free papers
Avail of top-rated report writing help on CE3116: Foundation Engineering (G). We have a panel of adept report writers who are skilled in all the aspects of report writings. Also, our report writers are effortlessly complete your report on engineering assignment at a market price.
Looking for Plagiarism free Answers for your college/ university Assignments.
- CM2015 Programming with Data Midterm Coursework Assignment 2026
- CM2030 Graphics Programming Assignment Brief 2026 | UOL
- AVET205 Veterinary Anatomy & Physiology (VAP) Practical Assignment 2026
- S2559C Advanced Integrated Care Planning Graded Assignment 2026
- S1519C Integrated Care and the Singapore Health System Graded Assignment 2026
- S3589C Project on Communication and Health Coaching Graded Assignment 2026
- PSB5037EE Manufacture of Electronic Systems for Regulatory Compliance Assignment CW 1
- A2859C Pharmacotherapeutics I Graded Assignment Brief 2026
- ISIT332 Business Process Management Individual Assignment 1
- A3740C Complementary and Alternative Medicine Graded Assignment